MIL-T-6211OG
(f) Arc-voltage, current range and polarity
(g) Manual or machine
(h) Travel speed, machine only
(i) Pre-heat and post-heat.
4. QUALITY ASSURANCE PROVISIONS
4.1 Responsibility for inspection. Unless otherwise specified in the contract, the contractor is responsible for the performance of all inspection requirements (examination and tests) as specified herein. Except as otherwise specified in the contract, the contractor may use his own or any other facilities suitable for the performance of the inspection requirements specified herein, unless disapproved by the Government. The Government reserves the right to perform any of the inspections set forth in the specification where such inspections are deemed necessary to assure supplies and services conform to prescribed requirements.
* 4.1.1 Responsibility for compliance. All items must meet all requirements of sections 3 and 5. The inspection set forth in this specification shall become a part of the contractor's
overall inspection system or quality program. The absence of any inspection requirements in the
specification shall not relieve the contractor of the responsibility for ensuring that all products or supplies submitted to the Government for acceptance comply with all requirements of the contract. Sampling inspection, as part of manufacturing operations is an acceptable practice to ascertain conformance to requirements, however this does not authorize submission of known defective material, either indicated or actual, nor does it commit the Government to acceptance
of defective material.
4.2 Government verification. Quality assurance operations performed by the contractor will be subject to Government verification at unscheduled intervals. Verification will consist of observation of the operations to determine that practices, methods, and procedures of the contractor's inspection are being properly applied. Failure of the contractor to promptly correct product deficiencies discovered shall be cause for suspension of acceptance until correction has been made or until conformance of product to specification criteria has been demonstrated.
4.3 First vehicle preliminary welding inspection.
4.3.1 Welding procedure and workmanship specimen evaluation. Prior to the start of the fabrication of the subframe, body, turret, outriggers, and derrick assemblies, an inspection shall be conducted by the Government to evaluate workmanship specimens and welding procedures.
4.3.1.1 Macro-etching. Workmanship specimens shall be cross-sectioned and macro-etched. Both parts of the specimens shall be made available to the Government representatives for examination.
49