MIL-V-62347(AT)
4.2 Classification of inspections. Classification of inspection shall be as follows:
a. First article (preproduction) inspection (see 4.3). b. Initial production vehicle inspection (see 4.4).
c. Quality conformance inspection (see 4.6).
4.3 First article (preproduction) inspection. One first article sample (see 3.1) shall be inspected, at a location approved by the Government, to determine conformance to requirements of this specification. Inspection shall consist of examination as specified in 4.6.2, and all tests specified herein.
4.3.1 Failure. Failure to pass any examination or test, or defects in excess of acceptable quality levels (AQLs) specified, shall be cause for refusal to grant first article approval.
4.4 Initial production vehicle inspection. On beginning production, (six) vehicles shall undergo, and shall pass, initial production inspection (see 3.2). One vehicle shall undergo first production vehicle inspection, and the second through sixth vehicle(s) will be subjected to the initial production test.
4.4.1 First production vehicle inspection.
4.4.1.1 In-process examination. During fabrication of the first production vehicle, an
in-process examination will be conducted by representatives of TACOM Product Assurance Directorate to evaluate conformance of materials and workmanship to specified requirements. Examination will be made at the contractor's or subcontractor's facility prior to application of primer and paint. Processing and welding procedures, quality system, and inspection records will be evaluated during this examination.
4.4.1.2 Completed first production vehicle contractor inspection. The first completed production vehicle shall be road tested and inspected by the contractor, as specified in 4.6.5, to determine conformance to contract and specifications. After inspection, the contractor shall submit the vehicle (and all inspection records and certifications) to the responsible Government inspection element at contractor's plant for preliminary examination.
4.4.1.3 Preliminary examination. The responsible Government inspection element will conduct a preliminary examination, as specified in 4.6.2, of the first completed production vehicle.
4.4.1.4 Provisional inspection. Provisional inspection of the first completed production vehicle will be conducted jointly by representatives of TACOM Product Assurance Directorate and the responsible Government inspection element. Contractor shall provide any required assistance. Testing will be as specified in 4.6.5. Contractor shall make available his inspection plan, records, and certifications pertinent to the vehicle and components.
20